Projects

Our Finest Work

Project 1

Medium Voltage Switchgear Changeout at a Texas Distributions Center. This changeout involved completely disassembling the existing deteriorating switchgear, replacing it with new state-of-the-art switchgear and cleaning up the jobsite, including trucking out the disassembled old gear. We were given a time frame to be down of 24 hrs. We were complete and off premise in 22 hrs.

Project 2 - Before

Switchgear lineup changeout at a Mississippi Distribution Center. This picture shows the pad after the old Switchgear had been removed. We had two simultaneous shutdowns in 2 different buildings going on with the removal of two large lineups, 4 large transformers and 3 separate smaller panels all at the same outage. Tear down, re-install, test, energize and cleanup was safely completed in 27 hours.

Project 2 - After

This is a picture of the above, (which was one of the Switchgear lineups), after we were complete.